Level II scour analysis for Bridge 34 (CONCTH00110034) on Town Highway 11, crossing Miles Stream, Concord, Vermont

Open-File Report 97-776
Prepared in cooperation with Vermont Agency of Transportation and Federal Highway Administration
By:  and 

Links

Abstract

This report provides the results of a detailed Level II analysis of scour potential at structure CONCTH00110034 on Town Highway 11 crossing Miles Stream, Concord, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (U.S. Department of Transportation, 1993). Results of a Level I scour investigation also are included in Appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gleaned from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in Appendix D. The site is in the New England Upland section of the New England physiographic province in northeastern Vermont. The 24.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is shrub and brush on the left bank upstream and downstream of the bridge. The surface cover on the right bank upstream is pasture while downstream it is forest. In the study area, Miles Stream has an incised, sinuous channel with a slope of approximately 0.005 ft/ft, an average channel top width of 48 ft and an average bank height of 4 ft. The channel bed material ranges from gravel to boulder with a median grain size (D50) of 102 mm (0.335 ft). The geomorphic assessment at the time of the Level I and Level II site visit on August 15, 1995, indicated that the reach was stable. The Town Highway 11 crossing of Miles Stream is a 38-ft-long, two-lane bridge consisting of one 36-foot concrete slab span (Vermont Agency of Transportation, written communication, March 16, 1995). The opening length of the structure parallel to the bridge face is 33.9 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is skewed approximately 20 degrees to the opening. The calculated opening-skewto-roadway is 25 degrees while the VTAOT determined opening-skew-to-roadway is 22 degrees. The scour countermeasures at the site included type-2 stone fill (less than 36 inches diameter) along the entire base length of all four wingwalls, scattered in front of the left and right abutments, and along the downstream left and right banks. Also, there is type-3 stone fill (less than 48 inches diameter) along the upstream left and right banks. Additional details describing conditions at the site are included in the Level II Summary and Appendices D and E. Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and others, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge is determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows. Contraction scour for all modelled flows ranged from 0.0 to 1.3 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. The right abutment scour ranged from 7.4 to 9.6 ft while the left abutment scour ranged from 12.8 to 14.4 ft. The worst-case abutment scour for the left and right abutments occurred at the 500-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scouredstreambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particlesize distribution. However, there is exposed bedrock in the channel upstream and downstream of the bridge. Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Study Area

Publication type Report
Publication Subtype USGS Numbered Series
Title Level II scour analysis for Bridge 34 (CONCTH00110034) on Town Highway 11, crossing Miles Stream, Concord, Vermont
Series title Open-File Report
Series number 97-776
DOI 10.3133/ofr97776
Year Published 1997
Language English
Publisher U.S. Geological Survey
Publisher location Pembroke, NH
Description iv, 51 p.
Country United States
State Vermont
City Concord
Other Geospatial Miles Stream
Scale 24000
Google Analytic Metrics Metrics page
Additional publication details