Level II scour analysis for Bridge 47 (PLYMTH00540047) on Town Highway 54, crossing Pinney Hollow Brook, Plymouth, Vermont

Open-File Report 98-196
Prepared in cooperation with Vermont Agency of Transportation and Federal Highway Administration
By:  and 

Links

Abstract

This report provides the results of a detailed Level II analysis of scour potential at structure PLYMTH00540047 on Town Highway 54 crossing Pinney Hollow Brook, Plymouth, Vermont (figures 1–8). A Level II study is a basic engineering analysis of the site, including a quantitative analysis of stream stability and scour (FHWA, 1993). Results of a Level I scour investigation also are included in appendix E of this report. A Level I investigation provides a qualitative geomorphic characterization of the study site. Information on the bridge, gathered from Vermont Agency of Transportation (VTAOT) files, was compiled prior to conducting Level I and Level II analyses and is found in appendix D.

The site is in the Green Mountain section of the New England physiographic province in south-central Vermont. The 7.9-mi2 drainage area is in a predominantly rural and forested basin. In the vicinity of the study site, the surface cover is pasture upstream and downstream of the bridge while the immediate banks have dense woody vegetation.

In the study area, Pinney Hollow Brook has an incised, straight channel with a slope of approximately 0.01 ft/ft, an average channel top width of 57 ft and an average bank height of 7 ft. The channel bed material ranges from sand to cobbles with a median grain size (D50) of 45.7 mm (0.150 ft). The geomorphic assessment at the time of the Level I and Level II site visit on March 30, 1995 and Level II site visit on October 2, 1995, indicated that the reach was stable.

The Town Highway 54 crossing of Pinney Hollow Brook is a 30-ft-long, two-lane bridge consisting of a 27-foot steel-stringer span (Vermont Agency of Transportation, written communication, March 22, 1995). The opening length of the structure parallel to the bridge face is 25.7 ft. The bridge is supported by vertical, concrete abutments with wingwalls. The channel is not skewed to the opening and the opening-skew-to-roadway is zero degrees.

Scour protection measures at the site included type-1 stone fill (less than 12 inches diameter) along the upstream left wingwall, the upstream right wingwall and the downstream end of the downstream left wingwall. Additional details describing conditions at the site are included in the Level II Summary and appendices D and E.

Scour depths and recommended rock rip-rap sizes were computed using the general guidelines described in Hydraulic Engineering Circular 18 (Richardson and Davis, 1995) for the 100- and 500-year discharges. In addition, the incipient roadway-overtopping discharge was determined and analyzed as another potential worst-case scour scenario. Total scour at a highway crossing is comprised of three components: 1) long-term streambed degradation; 2) contraction scour (due to accelerated flow caused by a reduction in flow area at a bridge) and; 3) local scour (caused by accelerated flow around piers and abutments). Total scour is the sum of the three components. Equations are available to compute depths for contraction and local scour and a summary of the results of these computations follows.

Contraction scour for all modelled flows ranged from 0.0 to 2.0 ft. The worst-case contraction scour occurred at the incipient roadway-overtopping discharge, which was less than the 100-year discharge. Left abutment scour ranged from 3.4 to 6.7 ft. The worst-case left abutment scour occurred at the 500-year discharge. Right abutment scour ranged from 8.9 to 9.6 ft. The worst-case right abutment scour occurred at the 100-year discharge. Additional information on scour depths and depths to armoring are included in the section titled “Scour Results”. Scoured-streambed elevations, based on the calculated scour depths, are presented in tables 1 and 2. A cross-section of the scour computed at the bridge is presented in figure 8. Scour depths were calculated assuming an infinite depth of erosive material and a homogeneous particle-size distribution.

It is generally accepted that the Froehlich equation (abutment scour) gives “excessively conservative estimates of scour depths” (Richardson and Davis, 1995, p. 46). Usually, computed scour depths are evaluated in combination with other information including (but not limited to) historical performance during flood events, the geomorphic stability assessment, existing scour protection measures, and the results of the hydraulic analyses. Therefore, scour depths adopted by VTAOT may differ from the computed values documented herein.

Publication type Report
Publication Subtype USGS Numbered Series
Title Level II scour analysis for Bridge 47 (PLYMTH00540047) on Town Highway 54, crossing Pinney Hollow Brook, Plymouth, Vermont
Series title Open-File Report
Series number 98-196
DOI 10.3133/ofr98196
Year Published 1998
Language English
Publisher U.S. Geological Survey
Publisher location Pembroke, NH
Description iv, 51 p.
Country United States
State Vermont
City Plymouth
Google Analytic Metrics Metrics page
Additional publication details