Geologic and seismic investigations, relocation of Route 3, grade separation at Route 62, southeast ramp in Bedford, Mass.
Links
- Document: Report
- Download citation as: RIS | Dublin Core
Abstract
The relocation of Route 3 in Bedford, Mass. requires extensive cuts for a grade separation at Route 62. This report contains only the results of the geologic and seismic studies that were made for the purpose of obtaining information that would aid in the construction of the inner and outer loops of the southeast ramp. The studies represent part of a cooperative program of the Massachusetts Department of Public Works and the United States Geological Survey. The work was performed in July 1953.
The site is located in the Wilmington and Lexington 7-1/2-minute quadrangle maps of the United States Geological Survey. Mr. M. E. Chandler and Mr. W. L. Carney, Massachusetts Department of Public works' Engineers, performed all pertinent survey work required for this project, and prepared the essential plans and profiles. Mr. Chandler also operated the seismic equipment and assisted in the preparation of the seismic velocity data.
Study Area
Publication type | Report |
---|---|
Publication Subtype | USGS Numbered Series |
Title | Geologic and seismic investigations, relocation of Route 3, grade separation at Route 62, southeast ramp in Bedford, Mass. |
Series title | Open-File Report |
Series number | 54-190 |
DOI | 10.3133/ofr54190 |
Year Published | 1954 |
Language | English |
Publisher | U.S. Geological Survey |
Publisher location | Boston, MA |
Description | 2 p. |
Country | United States |
State | Massachusetts |
City | Bedford |
Google Analytic Metrics | Metrics page |